2007 Project Update
|
 |
65%
Overall
|
The overall project status is 65% complete (with 40% of the construction completed).
The terminal is expected to be in operation by the end of 2008. |
|
|
|
Watch a time-lapsed video of slip-forming of tank #2 being raised at the Canaport LNG site
37 seconds
|
|
|
Take a 3D Tour of
the
Canaport LNG Terminal
15 minutes:19 seconds
|
|
|
|
December 2007 |
|
November 2007 |
|
|
|
September 2007 |
|
August 2007 |
|
|
|
July 2007 |
|
June 2007 |
|
|
|
April 27, 2007: First Tank Ground Shot |
|
April 2007 |
|
|
|
March 2007 |
|
February 2007 |
Onshore, the construction of temporary installations, such as office buildings and material staging areas, has been completed. The foundations for the construction of the LNG tanks and pipelines have also been erected. Preparations for the summer construction season, when the peak of construction is expected, are almost finished.
Offshore jetty construction is nearing completion.
The final pieces, called “jackets,” are
currently being fabricated in Newfoundland. The installation
of the jackets will commence as early as April 2007
and complete by October 2007. With favorable conditions,
offshore is expected to be complete this year, by the
start of the fourth quarter.
At springtime, the number of contractors and employees working on site will begin to increase. During the peak period of June and July, there will be as many as 700 people helping to install materials and construct the LNG tanks. |