2008 Project Update

76%
Overall

 

 

Watch a time-lapsed video of slip-forming of tank #2 being raised at the Canaport LNG site

37 seconds

  Click Here To Watch The Video...


 

Take a 3D Tour of the
Canaport LNG Terminal


15 minutes:19 seconds

  Click Here To Start The Tour...


 
May 2008
 
 
April 2008
March 2008
 
February 2008
January 2008

Onshore, the construction of temporary installations, such as office buildings and material staging areas, has been completed. The foundations for the construction of the LNG tanks and pipelines have also been erected. Preparations for the summer construction season, when the peak of construction is expected, are almost finished.

Offshore jetty construction is nearing completion. The final pieces, called “jackets,” are currently being fabricated in Newfoundland. The installation of the jackets will commence as early as April 2007 and complete by October 2007. With favorable conditions, offshore is expected to be complete this year, by the start of the fourth quarter.

At springtime, the number of contractors and employees working on site will begin to increase. During the peak period of June and July, there will be as many as 700 people helping to install materials and construct the LNG tanks.

 
 
CanaPort - LNG Saint John, New Brunswick, Canada - Irving Oil Limited And Repsol YPF